How long does a Transmission Owner have to notify PJM of a communication capability failure that lasts 30 minutes or longer?

Prepare for the PJM Transmission Test. Study with flashcards and multiple choice questions, each question includes hints and explanations. Boost your readiness!

Multiple Choice

How long does a Transmission Owner have to notify PJM of a communication capability failure that lasts 30 minutes or longer?

Explanation:
A Transmission Owner is required to promptly notify PJM of any communication capability failures that last for 30 minutes or longer. The time frame of 60 minutes is established to ensure timely communication regarding outages or failures that may impact the reliability of the transmission system. This requirement helps PJM coordinate the necessary responses and maintain operational awareness. Addressing issues within this time frame allows for efficient management of resources and ensures that all stakeholders are informed and can take appropriate actions to uphold grid reliability.

A Transmission Owner is required to promptly notify PJM of any communication capability failures that last for 30 minutes or longer. The time frame of 60 minutes is established to ensure timely communication regarding outages or failures that may impact the reliability of the transmission system. This requirement helps PJM coordinate the necessary responses and maintain operational awareness. Addressing issues within this time frame allows for efficient management of resources and ensures that all stakeholders are informed and can take appropriate actions to uphold grid reliability.